Tornado Damage 2010
April 26th, 2010On April 24th, at around 11 AM, a powerful EF-3 tornado hit the Complex Chemical Co., Inc. plant, head on. At the time, 12 employees were at the plant. We are grateful that none of them were injured seriously, but three did sustain minor injuries. Three days after the event, the plant was open to Complex personnel for assessment, and subsequent planning. In the middle of all this, however, there was good news. The spill prevention system worked like it was designed. No materials left the confines of the plant. The eleven processing units, survived with only peripheral damage. The laboratory and heaters all survived with very little damage. Our central server that contained all our business records survived, as well as many crucial files. |
Photo Gallery - Click on photos for larger photo
|
May 3, 2010
|
We are now in week three of the recovery process. As can be seen, there has been tremendous progress in the area of clean up, and debris removal. Many, many containers of scrap metal and other debris have been hauled away. Large areas of concrete that was once covered with debris, are now open, and visible. The main driveways have been cleared so truck shipments can be made from inventory that was on hand prior to the storm.
|
May 17th, 2010
|
June 1st, 2010 |
June 14th, 2010 This photo shows the most dramatic change to date. At this point in time all eleven processing units are operating successfully and making product. All were brought up in the time frame set on 5/07/2010. Complex in these areas is at 90% of capacity. This is a major, major credit to our core management team and all the employees. Limitations exist in the area of drum filling but progress is being made there. The only outsourcing of production now is the area of packaging and drumming. Permanent re-construction has commenced in areas where it can be done, both in the electrical and piping areas. |
June 28, 2010
|
July 11, 2010
|
September 11, 2010Progress at this point is less visible from the outside. This is due to repairs being refocused on internal needs such as electrical and piping. Electricity has been restored to most sections of the plant and almost all generators are gone since they are no longer needed. One change that can be seen from the air is several small, temporary buildings that have been put up. These temporary structures are in place to help Complex continue meeting the needs of our customers. They will eventually be removed and replaced by permanent warehousing. It is worth noting that these photos come almost four months to the day after the tornado hit. Now, as in the beginning, the men and women of Complex continue to tackle each day’s challenges with heart, soul and determination that should stand as an example to all. After four months of almost continuous work it is clear that the focus of the Complex family is not just a temporary state but a permanent attitude. |
October 7, 2010Work at Complex is now shifting away from clean up and repair to new construction and rebuilding. These two photos highlight the new buildings that will house the main electrical breakers. The buildings are of heavy construction and elevated off the ground to provide maximum protection for the equipment inside. |
October 7, 2010The red steel being raised here will be used to form a large enclosure that will include both the distillation and oil blending units. This impressive structure will include the truck loading area as well to provide additional protection from the weather for products. |
November 15, 2010 These photos mark a large milestone for Complex Chemicals and its employees. The first new, permanent structure can be clearly seen now. This building covers the oil blending and distillation areas and includes loading and unloading facilities for oil blending. Operations in these areas are now protected from the weather in regards to rain, wind, etc. The next permanent building in line will be a large warehouse that will cover the concrete slap adjacent to the new structure. This warehouse will be used to store raw materials and provide a spot for our filling lines. What a difference seven months has made. |
January 7, 2011 Small steps have given way to larger ones as these photos clearly show. The new warehouse will provide nearly 50,000 square feet of operation and storage space. An added bonus of the warehouse is it has allowed us to remove many of the storage containers we have been using. Another improvement is additional concrete in several key “traffic” areas. These extra slabs will make all loading and unloading operations run smother and faster, increasing turn around time. The rebuilding of the electrical system continues and many feet of new “cable trays” have been built through out the plant. By the large open topped tank the dirt work for the new nitrogen plant can be seen as well. |
March 10, 2011Complex continues to move ahead in rebuilding. The new nitrogen plant is now in place. Many more containers have been removed and there contents moved to the new warehouse. In the back area a new roof is over the secondary oil loading and unloading area and several doors are now in place on the main warehouse as it nears completion. General clean up continues and new concrete is still being laid. Some of the new electrical has been completed and is servicing certain areas of the plant. Thanks again to all our team members that have made this happen. |
April 29, 2011These aerial photos are 1 year and five days after the tornado roared through so many peoples’ lives, starting just a little way west of Complex and traveling almost 175 miles into Mississippi leaving a terrible path of death and destruction. I have so much to be grateful for. No Complex employees were seriously injured. None of our faithful customers gave up on us. I have the hardest working, toughest, most resilient, creative employees anyone could ever ask for. Our business has actually expanded in the year since the storm. |
Jan 14th, 2012Nearly 20 months after the tornado hit, the final pages of this chapter in Complex Chemicals history are ready to be written. The last step in the original reconstruction plan, the new office building has gone up and can be easily seen. The hard working, dedicated men and women of the Complex family can now see and say with absolute confidence that with the grace of God their company has survived, overcome and conquered its greatest challenge to date. It has been a long journey and the last purpose driven steps are now being taken. |






















